HLNEO - Chronology Page
Monticello Blvd. Bridge Over Euclid Creek
The timeline of structures at this location reflects our best information to date and is NOT guaranteed to be complete.
Structure # 1
|
|
Bridge Type: | Concrete Arch |
| Years Existed: | 1955-Present | |
| Background Information: | The Monticello Boulevard Bridge over Euclid Creek was built in 1955. The bridge is a three-span, concrete arch, that has a center span of 140 feet with the two side spans being 108 feet each. The bridge has two 28-foot roadways and was designed by Osborn Engineering Company. Source: Bridges of Metropolitan Cleveland. | |
| MORE INFORMATION |